FocalPoint is the answer of Beverly Hills

Los Angeles County has stormwater regulation standards required for a Beverly Hills project, and FocalPoint was the answer!

In addition, the owner will save $29,000!!

Problem: 

  1. The challenge was that there was not enough space for a traditional pre-cast concrete system.
  2. Cost of pre-cast concrete system = $58,000

Solution:

  1. FocalPoint has the ability to split, scale and fit where there is space for it.  California Filtration Specialists designed a 60’ x 2.5’ biofiltration system which fit between the building and adjacent sidewalk.
  2. Cost of FocalPoint biofiltration system = $29,000